Munich – Horizontal Auger Boring Ottostraße
Crossing under the Tram through horizontal auger boring for district cooling in Ottostraße
vesting period:
construction time period:
length of marked-out route:
pipe diameter:
house connections:
x
boring under the Tram:
Length off boring:
12/2012 until 03/2013
04/2013 until 06/2014
ca. 850 m
2 x DN 400 preinsulated pipes
2 x DN 150 preinsulated pipes and
1 x DN 80 preinsulated pipes
2 x DN 800 Steel
ca. 30 m
Branch
Underground and Pipeline Construction
Special Underground Construction
Microtunnelling
Concrete construction
Tram crossing contract
Services
Preplanning
Implementation planning
Local construction supervision
Safety coordination
Traffic planning