Munich – district heating Schellingstraße

District heating – ReHa Görres-, Schellingstraße (refurbishment)

Vesting period:
Construction time period:
Pipe diameter:
House connections:

10/2012 until 10/2013
04/2013 until 11/2013
approximately 1.500 m DN 250 up to DN 500
94 m DN 25 up to DN 65 (12 pcs.)

Services
Implementation planning for underground and pipeline construction
Pipe stress analysis
Traffic planning
Tender of performance directory
Safety and health coordination
Local construction supervision

Details
Enclosing / involvement in several existing shafts
Decommissioning of 10 shafts
Change of hood canal to preinsulated pipes with expansion and damming the hood
Construction / enclose in operation
High traffic
Confined urban conditions