Munich – district heating Maximilianplatz

Expansion of district heating pipe – Enclosing during operation

Vesting period:
Construction time period:
Pipe diameter:
House connections:
Length of marked-out route:

02/2013 until 08/2013
05/2013 until 11/2013
DN 65 and 80 preinsulated pipes
5 pcs., DN 65 up to DN 80
approximately 250 m

Services
Implementation planning for underground and pipeline construction
Pipe stress analysis
Tender of performance directory
Local construction supervision

Details
Refurbishment
Relocation / renovation of several building lines
Provisional supply via a 40 m long bridge auxiliary line
archaeological monitoring of construction
management of corresponding work