Berg at the Starnberger Lake – Drinking water line
Construction of a new drinking water line by means of a plow
Vesting period:
Construction time period:
Taken plowed line:
gdgdg
Total length:
part in conventional tillage:
04/2013
05/2013 until 07/2013
Drinking water pipe – DN 80 PE
Conduit – DN 80 PE
approximately 410 m
approximately 350 m
Services:
Implementation planning for underground and pipeline construction
Tender of performance directory
Local construction supervision