Augsburg – district heating Obstmarkt
Rehabilitation of a district heating pipe – Enclosing during operation
Vesting period:
Construction time period:
Pipe diameter:
House connections:
Length of marked-out route:
2012 until 10/2013
04/2013 until 08/2013
DN 32 and DN 100 preinsulated pipes
DN 32 up to DN 80
approximately 370 m
Services
Implementation planning for underground and pipeline construction
Traffic planning
Pipe stress analysis
Tender of performance directory
Local construction supervision
Details
Removing a hood canal
Rebuild in DN 150/150 preinsulated pipes
New / relocation of a building line
Build by archaeological standards due to bone finds and excavations